title: How do I back-calculate submittal due dates from the schedule and send a weekly due-soon list? | AEC Agents
url: https://aecagents.si/use-cases/submittal-due-dates-from-schedule
description: Join the submittal log to schedule activities, subtract lead time and review time from the need-on-site date, and email the team a list of submittals that must move in the next two weeks.
last_modified: 2026-11-27
source: AEC Agents (free, open workflows; not engineering advice)
---

[AI assists](https://aecagents.si/use-cases/submittal-due-dates-from-schedule#honesty-labels)Workflow guide · not independently tested

# How do I back-calculate submittal due dates from the schedule and send a weekly due-soon list?

Join the submittal log to schedule activities, subtract lead time and review time from the need-on-site date, and email the team a list of submittals that must move in the next two weeks.

Role
:   [Project Manager](https://aecagents.si/roles/project-manager)

Discipline
:   Construction

Tools
:   Microsoft Excel, Procore submittals

Updated
:   27 November 2026

Tool links listed below; vendor features and pricing change, so confirm with the vendor.

## Short answer

Use Copilot in Excel or Gemini in Google Sheets: The AI matches submittals to schedule activities and builds the submit-by formulas and the two-week due list. Join the submittal log to schedule activities, subtract lead time and review time from the need-on-site date, and email the team a list of submittals that must move in the next two weeks. A person still checks: activity matches and lead times with the subs.

## AI tie-in

**Tool:** Copilot in Excel or Gemini in Google Sheets

The AI matches submittals to schedule activities and builds the submit-by formulas and the two-week due list.

### Prompt 1

```
Sheet 1 is my submittal log, sheet 2 is the schedule. Suggest the matching activity for each submittal, add columns for lead time and review days, compute submit-by = activity start - lead time - review - 7 days, and make a tab listing anything due in the next 14 days that isn't approved.
```

**Human check:** Activity matches and lead times with the subs.

## The problem

Back-calculate submittal due dates from the schedule and send a weekly due-soon list. This is a common, time-consuming task for a project manager.

## What this workflow does

Join the submittal log to schedule activities, subtract lead time and review time from the need-on-site date, and email the team a list of submittals that must move in the next two weeks.

**How it works:** AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

**Your checkpoint:** Lead times come from subs and change. Dates are only as good as the activity links and schedule updates.

## Before you start

- Access to the named tool; confirm license, version and cost with the vendor.
- A small, non-confidential sample to try the workflow on first.
- A qualified person to review the output before it is used.

### Tools and access

- [Microsoft Excel](https://www.microsoft.com/microsoft-365/excel)
- [Procore submittals](https://www.procore.com/)

## Follow the steps

1. Export the submittal log and the schedule to spreadsheets.
2. Add columns: linked activity ID, sub lead time, review duration, buffer.
3. Compute required submit-by date = activity start - lead time - review - buffer.
4. Filter to items due within 14 days and not yet approved.
5. Send that list weekly (saved report or scheduled email) to the PE and supers.
6. Refresh after each schedule update.

## Try a small example

Replace the bracketed fields with your own project details. No tested sample run is published for this workflow yet.

### Sample input

```
Fill in the bracketed [fields] in the text below with your project data.
```

### Starter prompt

```
From this submittal log and schedule export, match each submittal to the most likely activity, list lead time assumptions to confirm, and compute submit-by dates. Mark any match you are unsure of: [paste data]
```

### Expected output

```
Not published yet. Treat any output as a draft and check it against the source documents.
```

## Check the result

- Every value, citation or quantity traces back to a source document.
- Missing information is marked as missing, not filled in.

## Limits and recovery

- Lead times come from subs and change. Dates are only as good as the activity links and schedule updates.
- Check your organization’s data policy before sharing project files with third-party tools.

**Stop or switch when:** The source cannot be verified, permissions are missing, or the result contains unsupported facts.

## Frequently asked questions

How does AI help with this?

Copilot in Excel or Gemini in Google Sheets: The AI matches submittals to schedule activities and builds the submit-by formulas and the two-week due list. A person still checks: Activity matches and lead times with the subs.

How do I how do I back-calculate submittal due dates from the schedule and send a weekly due-soon list??

Export the submittal log and the schedule to spreadsheets. Add columns: linked activity ID, sub lead time, review duration, buffer. Compute required submit-by date = activity start - lead time - review - buffer. The full step list is above.

Does this use an AI agent or regular software?

It is labeled AI assists: AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

What tools do I need?

Microsoft Excel, Procore submittals. Confirm license, version and cost with the vendor, and try it on a small non-confidential sample first.

Has this workflow been tested?

Workflow guide · not independently tested. It is written from vendor documentation and practitioner use.

## Where to go next

- [How do I search project documents with AI to answer field questions, then confirm the source?](https://aecagents.si/use-cases/project-document-search)
- [How do I compare construction schedule scenarios with AI-assisted scheduling tools?](https://aecagents.si/use-cases/schedule-optimization)
- [How do I spot schedule delays and quality problems early with schedule analytics?](https://aecagents.si/use-cases/schedule-health)
- [All Project Manager workflows](https://aecagents.si/roles/project-manager)
- [All Design calcs and analysis workflows](https://aecagents.si/tasks/design-calcs)

## Evidence and maintenance

Written from vendor documentation and practitioner use. Labels apply to the steps described here, not every feature of a product. Links were checked when the page was written.

- [Microsoft Excel (vendor site)](https://www.microsoft.com/microsoft-365/excel)
- [Procore submittals (vendor site)](https://www.procore.com/)

## On this page

Start with a small sample and keep the original record open while you verify the result.

## How each workflow is labeled

Agent executes
:   An AI agent calls connected tools to carry out bounded actions. You set permissions and review the result.

AI assists
:   AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

Conventional automation
:   Rules or specialist software perform the task. No AI agent is required.