title: How do I turn my estimate into a schedule of values with AI so it adds up to the contract and isn't front-loaded? | AEC Agents
url: https://aecagents.si/use-cases/schedule-of-values-from-estimate-markup-spread
description: Build the schedule of values from your estimate's cost-code totals, not a blank sheet: group the codes into billable lines, spread overhead and profit across every line in proportion to its cost (cost times contract sum divided by total cost), round to the dollar and hand the few leftover dollars to the largest fractions so the lines total the contract sum exactly. Have Claude or ChatGPT read your estimate summary into one Estimate tab with a SOV Line for each cost code, then have Copilot in Excel, Gemini in Google Sheets or a short script build the proportional schedule and flag unmapped or duplicated cost codes, lines over the caps your contract sets, lines too big to bill month by month, and any proposed line that sits well above its proportional value (front-loading); the line breakdown and caps come from your contract, and the schedule is approved by the architect or owner, not by the check.
last_modified: 2026-11-27
source: AEC Agents (free, open workflows; not engineering advice)
---

[AI assists](https://aecagents.si/use-cases/schedule-of-values-from-estimate-markup-spread#honesty-labels)Workflow guide · not independently tested

# How do I turn my estimate into a schedule of values with AI so it adds up to the contract and isn't front-loaded?

Build the schedule of values from your estimate's cost-code totals, not a blank sheet: group the codes into billable lines, spread overhead and profit across every line in proportion to its cost (cost times contract sum divided by total cost), round to the dollar and hand the few leftover dollars to the largest fractions so the lines total the contract sum exactly. Have Claude or ChatGPT read your estimate summary into one Estimate tab with a SOV Line for each cost code, then have Copilot in Excel, Gemini in Google Sheets or a short script build the proportional schedule and flag unmapped or duplicated cost codes, lines over the caps your contract sets, lines too big to bill month by month, and any proposed line that sits well above its proportional value (front-loading); the line breakdown and caps come from your contract, and the schedule is approved by the architect or owner, not by the check.

Role
:   [Project Manager](https://aecagents.si/roles/project-manager)

Discipline
:   Construction

Tools
:   Claude, ChatGPT, Microsoft Excel, Microsoft Copilot, Google Sheets, Gemini

Updated
:   27 November 2026

Tool links listed below; vendor features and pricing change, so confirm with the vendor.

## Short answer

Use Claude or ChatGPT, then Copilot in Excel or Gemini in Google Sheets: Claude or ChatGPT reads the estimate summary into one Estimate tab with your SOV Line for each cost code; Copilot or Gemini (or a short script) totals cost by line, spreads the contract sum in proportion to cost, rounds to the dollar so the lines total the contract exactly, and flags unmapped or duplicated codes, lines over your contract's caps, lines too big to bill monthly and proposed lines well above their proportional value. Build the schedule of values from your estimate's cost-code totals, not a blank sheet: group the codes into billable lines, spread overhead and profit across every line in proportion to its cost (cost times contract sum divided by total cost), round to the dollar and hand the few leftover dollars to the largest fractions so the lines total the contract sum exactly. Have Claude or ChatGPT read your estimate summary into one Estimate tab with a SOV Line for each cost code, then have Copilot in Excel, Gemini in Google Sheets or a short script build the proportional schedule and flag unmapped or duplicated cost codes, lines over the caps your contract sets, lines too big to bill month by month, and any proposed line that sits well above its proportional value (front-loading); the line breakdown and caps come from your contract, and the schedule is approved by the architect or owner, not by the check. A person still checks: the mapping of codes to lines, every flag, the line total against the contract sum and any caps against the contract before the schedule goes out; the line breakdown and caps come from the contract and Division 01, and the schedule is approved by the architect or owner, not by the check.

## AI tie-in

**Tool:** Claude or ChatGPT, then Copilot in Excel or Gemini in Google Sheets

Claude or ChatGPT reads the estimate summary into one Estimate tab with your SOV Line for each cost code; Copilot or Gemini (or a short script) totals cost by line, spreads the contract sum in proportion to cost, rounds to the dollar so the lines total the contract exactly, and flags unmapped or duplicated codes, lines over your contract's caps, lines too big to bill monthly and proposed lines well above their proportional value.

### Prompt 1

```
Read this estimate summary [upload the estimate PDF or paste the export] and build one Estimate table: Code, Description, Cost, SOV Line. Copy each cost exactly as shown, with no rounding. Use only these SOV Line names, which I chose: [paste your line names]. Put each code on the line that matches how the work is installed; if a code does not clearly fit one line write UNMAPPED instead of guessing. Then list every code that appears more than once, every subtotal you skipped so it is not counted twice, and the total of the Cost column so I can check it against the estimate's grand total.
```

### Prompt 2

```
EXAMPLE DATA ONLY (not from a real project). Estimate tab: Code, Description, Cost, SOV Line. Proposed tab (optional): SOV Line, Proposed. Rules typed by me: contract sum 560,000; caps of 2% for Mobilization and 4.5% for Bonds and insurance; no line over 30% of the contract; flag a proposed line more than 10% over its proportional value. Write Excel formulas (or a step-by-step Copilot plan) that flag codes with no SOV Line and rows with the same code, description and cost twice and leave them out; total cost by SOV Line; compute each line as cost x contract sum / total cost, rounded down to the dollar, then add 1 dollar to the lines with the largest fractions until the lines total the contract sum exactly; flag lines over their cap or over 30% of the contract; then compare the Proposed tab with the proportional values, flag lines more than 10% over, proposed lines over a cap, and a proposed total that is not the contract sum. Use only my rows and rules; do not supply any cap, markup or line breakdown from memory.
```

**Human check:** The mapping of codes to lines, every flag, the line total against the contract sum and any caps against the contract before the schedule goes out; the line breakdown and caps come from the contract and Division 01, and the schedule is approved by the architect or owner, not by the check.

## The problem

Turn a winning estimate into a schedule of values with AI so the lines add up to the contract and nothing is front-loaded. This is a common, time-consuming task for a project manager.

## What this workflow does

Build the schedule of values from your estimate's cost-code totals, not a blank sheet: group the codes into billable lines, spread overhead and profit across every line in proportion to its cost (cost times contract sum divided by total cost), round to the dollar and hand the few leftover dollars to the largest fractions so the lines total the contract sum exactly. Have Claude or ChatGPT read your estimate summary into one Estimate tab with a SOV Line for each cost code, then have Copilot in Excel, Gemini in Google Sheets or a short script build the proportional schedule and flag unmapped or duplicated cost codes, lines over the caps your contract sets, lines too big to bill month by month, and any proposed line that sits well above its proportional value (front-loading); the line breakdown and caps come from your contract, and the schedule is approved by the architect or owner, not by the check.

**How it works:** AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

**Your checkpoint:** The check is arithmetic on the rows and rules you type. It cannot tell whether your contract requires a different breakdown (by area, spec section or material versus labor), whether general conditions, bonds or mobilization must be their own lines or spread, whether stored materials need separate lines, or whether an owner will accept a line split; read the contract and Division 01 for those. Proportional spread is a common, even-handed default, not a rule; if you carry markup differently, type it that way. Caps and tolerances here are typed example values, not a standard.

## Before you start

- Access to the named tool; confirm license, version and cost with the vendor.
- A small, non-confidential sample to try the workflow on first.
- A qualified person to review the output before it is used.

### Tools and access

- [Claude (Anthropic)](https://www.anthropic.com/claude)
- [ChatGPT](https://chatgpt.com/)
- [Microsoft Excel](https://www.microsoft.com/microsoft-365/excel)
- [Microsoft Copilot](https://www.microsoft.com/microsoft-365/copilot)
- [Google Sheets](https://workspace.google.com/products/sheets/)
- [Gemini](https://gemini.google.com/)

## Follow the steps

1. Start from the estimate, not from the billing form: export or copy the summary by cost code with the cost of each code (not quantities or hours), plus the executed contract sum before any change orders. Read the contract and Division 01 for any required breakdown, caps on mobilization, bonds or general conditions, and whether those must be their own lines.
2. Have Claude or ChatGPT read the estimate summary (upload the PDF or paste the export) into one Estimate tab: Code, Description, Cost, SOV Line. You decide the SOV Line names; group codes the way the work is installed and inspected, usually 10 to 30 lines, and keep the same lines for the whole job. It copies costs exactly, writes UNMAPPED instead of guessing a line, and lists any code that appears twice.
3. On a Rules tab, type the contract sum, any caps your contract or the owner set (as a share of the contract), the largest share you are willing to bill in one line, and how far over its proportional value a line may sit before you call it front-loaded. Have Copilot in Excel or Gemini in Google Sheets (or the script below) total cost by line, multiply each by contract sum divided by total cost, round down to the dollar and give the leftover dollars to the lines with the largest fractions.
4. If someone already drafted a schedule (yours, a sub's, or one the owner sent back), paste it as a Proposed tab and compare it line by line with the proportional values: lines well above proportional are the ones an owner's reviewer will ask backup for, and the proposed total must equal the contract sum to the dollar.
5. Clear every flag before the schedule goes in with the first pay application: map or delete unmapped codes (they inflate every other line's markup), confirm duplicates, split lines too big to bill monthly, fix any line over a cap, and keep change orders as their own lines after the original schedule instead of folding them into it.

## Try a small example

EXAMPLE DATA ONLY: fictional cost codes, costs, caps and contract sum for practice, not from a real project or a published trial. The caps and tolerance are typed for this demo, not taken from any contract form or standard; type yours from your own contract. Paste the Sample input into Copilot or Gemini with the Starter prompt, then compare your results to Expected output.

### Sample input

```
Estimate tab (example, saved as estimate.csv; SOV Line is chosen by you, blank = not mapped yet)
Code,Description,Cost,SOV Line
01-100,Supervision and project management,61500,General conditions
01-500,Temporary facilities and cleanup,18200,General conditions
01-700,Payment and performance bond,14800,Bonds and insurance
01-710,Builder's risk and GL allocation,9600,Bonds and insurance
01-900,Mobilization,7500,Mobilization
02-410,Selective demolition,28400,Demolition
03-300,Slab infill and patching,22750,Concrete
05-400,Cold-formed framing,41300,Framing and drywall
09-210,Gypsum board assemblies,118600,Framing and drywall
09-220,Drywall finishing upgrade,12400,
09-510,Acoustical ceilings,46900,Ceilings
09-650,Resilient flooring,38250,Flooring
09-910,Painting,27300,Painting
08-110,Doors frames and hardware,52100,Doors and hardware
08-110,Doors frames and hardware,52100,Doors and hardware

Proposed tab (example draft schedule to compare, saved as proposed.csv)
SOV Line,Proposed
General conditions,104000
Bonds and insurance,26000
Mobilization,40000
Demolition,31000
Concrete,25000
Framing and drywall,154000
Ceilings,50000
Flooring,40000
Painting,30000
Doors and hardware,60000

Rules typed by you (example values): contract sum $560,000; caps 2% Mobilization and 4.5% Bonds and insurance; no line over 30% of the contract; flag a proposed line more than 10% over its proportional value
```

### Starter prompt

```
EXAMPLE DATA ONLY (not from a real project). Estimate tab: Code, Description, Cost, SOV Line. Proposed tab (optional): SOV Line, Proposed. Rules typed by me: contract sum 560,000; caps of 2% for Mobilization and 4.5% for Bonds and insurance; no line over 30% of the contract; flag a proposed line more than 10% over its proportional value. Write Excel formulas (or a step-by-step Copilot plan) that flag codes with no SOV Line and rows with the same code, description and cost twice and leave them out; total cost by SOV Line; compute each line as cost x contract sum / total cost, rounded down to the dollar, then add 1 dollar to the lines with the largest fractions until the lines total the contract sum exactly; flag lines over their cap or over 30% of the contract; then compare the Proposed tab with the proportional values, flag lines more than 10% over, proposed lines over a cap, and a proposed total that is not the contract sum. Use only my rows and rules; do not supply any cap, markup or line breakdown from memory.
```

### Expected output

```
Expected results on this example (output of the script below on these rows)
Estimate cost $487,200; contract $560,000; every line carries 14.94% on cost

SOV line                     Cost  Scheduled value   Share
Framing and drywall       159,900          183,793   32.8%
General conditions         79,700           91,609   16.4%
Doors and hardware         52,100           59,885   10.7%
Ceilings                   46,900           53,908    9.6%
Flooring                   38,250           43,966    7.9%
Demolition                 28,400           32,644    5.8%
Painting                   27,300           31,379    5.6%
Bonds and insurance        24,400           28,046    5.0%
Concrete                   22,750           26,149    4.7%
Mobilization                7,500            8,621    1.5%
Total                     487,200          560,000

Proposed SOV vs proportional
SOV line                 Proposed  Proportional      Diff
Bonds and insurance        26,000        28,046    -2,046
Ceilings                   50,000        53,908    -3,908
Concrete                   25,000        26,149    -1,149
Demolition                 31,000        32,644    -1,644
Doors and hardware         60,000        59,885      +115
Flooring                   40,000        43,966    -3,966
Framing and drywall       154,000       183,793   -29,793
General conditions        104,000        91,609   +12,391
Mobilization               40,000         8,621   +31,379
Painting                   30,000        31,379    -1,379
Total                     560,000       560,000        +0

Flags (clear each before the SOV goes out with the first pay application):
 - 09-220 Drywall finishing upgrade: $12,400 not mapped to any SOV line; NOT counted, so the markup below is too high until you map it
 - 08-110: same code, description and cost twice; counted once; confirm it is not two real items
 - Framing and drywall: 32.8% of the contract in one line; split it so it can be billed month by month
 - Bonds and insurance: 5.0% of the contract, over the 4.5% cap typed from the contract
 - Bonds and insurance: proposed $26,000 is 4.6% of the contract, over the 4.5% cap
 - General conditions: proposed $104,000 is 14% over its proportional $91,609; front-loaded unless the backup supports it
 - Mobilization: proposed $40,000 is 7.1% of the contract, over the 2.0% cap
 - Mobilization: proposed $40,000 is 364% over its proportional $8,621; front-loaded unless the backup supports it
Arithmetic only. Line breakdown, caps and what the contract allows come from your contract and the owner; the SOV is approved by the architect or owner, not by this check.

Read it this way: the mapped estimate costs $487,200 against a $560,000 contract, so every line carries the same 14.94% on its cost: General conditions $79,700 x 560,000 / 487,200 = $91,609.20, and so on down the list. Rounding every line down leaves $4 short of the contract; those 4 dollars go to the four lines with the largest fractions, so the schedule lands on $560,000 exactly. Two estimate rows were held out on purpose: the $12,400 drywall finishing upgrade has no SOV Line (map it to Framing and drywall and every line's markup drops to 12.09%), and the doors code was pasted twice ($52,100 would have been billed twice). The draft schedule totals the contract sum, but it carries $40,000 on Mobilization, 7.1% of the contract and 4.6 times its proportional value, and $104,000 on General conditions, 14% over proportional; that is front-loading, and the dollars came out of Framing and drywall, which is already 32.8% of the contract in one line and should be split (for example framing, board, finishing) so it can be billed as it is done.

Suggested Excel logic (write against your own sheet layout; ContractSum, MaxShare and Tol are named cells, caps are a lookup on your Rules tab)
- Cost by line: =SUMIFS(Estimate[Cost],Estimate[SOV Line],A2,Estimate[Keep],TRUE) where Keep is FALSE for unmapped or duplicate rows (duplicate: =COUNTIFS(Estimate[Code],[@Code],Estimate[Description],[@Description],Estimate[Cost],[@Cost])>1 on the second and later rows).
- Exact share: =B2*ContractSum/SUM(B:B). Rounded down: =ROUNDDOWN(C2,0). Fraction (helper column E): =C2-D2. Leftover dollars: =ContractSum-SUM(D:D). Scheduled value: =D2+(RANK.EQ(E2,E$2:E$11)<=Leftover) (break any ties by hand).
- Flags: =D2/ContractSum>XLOOKUP(A2,Rules[Line],Rules[Cap],1); =D2/ContractSum>MaxShare; =XLOOKUP(A2,Proposed[SOV Line],Proposed[Proposed])-D2>Tol*D2; =SUM(Proposed[Proposed])<>ContractSum.

Same check as a short Python script (our own code; reads the rows above saved as estimate.csv and proposed.csv)
import csv
from collections import defaultdict

# Typed by you from the contract and your own estimate (example values only)
CONTRACT_SUM = 560000        # executed contract sum, before any change orders
CAPS = {"Mobilization": 0.02, "Bonds and insurance": 0.045}  # caps your contract or the owner set, as a share of the contract
MAX_LINE_SHARE = 0.30        # lines bigger than this are hard to bill monthly; your call
FRONT_LOAD_TOL = 0.10        # proposed line more than 10% over its proportional value gets flagged

rows = list(csv.DictReader(open("estimate.csv", encoding="utf-8-sig")))
flags, seen, cost = [], set(), defaultdict(float)
for r in rows:
    key = (r["Code"], r["Description"], r["Cost"])
    if key in seen:
        flags.append(f"{r['Code']}: same code, description and cost twice; counted once; confirm it is not two real items"); continue
    seen.add(key)
    c = float(r["Cost"] or 0)
    if c <= 0:
        flags.append(f"{r['Code']}: cost {c:,.0f}; check it"); continue
    if not r["SOV Line"].strip():
        flags.append(f"{r['Code']} {r['Description']}: ${c:,.0f} not mapped to any SOV line; NOT counted, so the markup below is too high until you map it"); continue
    cost[r["SOV Line"].strip()] += c

total_cost = sum(cost.values())
factor = CONTRACT_SUM / total_cost
exact = {k: v * factor for k, v in cost.items()}
sov = {k: int(v) for k, v in exact.items()}                   # round down to the dollar...
left = CONTRACT_SUM - sum(sov.values())
for k in sorted(exact, key=lambda k: exact[k] - sov[k], reverse=True)[:left]:
    sov[k] += 1                                               # ...then hand the leftover dollars to the largest fractions

print(f"Estimate cost ${total_cost:,.0f}; contract ${CONTRACT_SUM:,.0f}; every line carries {factor - 1:.2%} on cost\n")
print(f"{'SOV line':22} {'Cost':>10} {'Scheduled value':>16} {'Share':>7}")
for k in sorted(sov, key=lambda k: -sov[k]):
    share = sov[k] / CONTRACT_SUM
    print(f"{k:22} {cost[k]:10,.0f} {sov[k]:16,} {share:7.1%}")
    if k in CAPS and share > CAPS[k]:
        flags.append(f"{k}: {share:.1%} of the contract, over the {CAPS[k]:.1%} cap typed from the contract")
    if share > MAX_LINE_SHARE:
        flags.append(f"{k}: {share:.1%} of the contract in one line; split it so it can be billed month by month")
print(f"{'Total':22} {total_cost:10,.0f} {sum(sov.values()):16,}")

try:
    prop = {r["SOV Line"].strip(): float(r["Proposed"]) for r in csv.DictReader(open("proposed.csv", encoding="utf-8-sig"))}
except FileNotFoundError:
    prop = {}
if prop:
    print(f"\nProposed SOV vs proportional\n{'SOV line':22} {'Proposed':>10} {'Proportional':>13} {'Diff':>9}")
    for k in sorted(set(prop) | set(sov)):
        p, s = prop.get(k), sov.get(k)
        if p is None or s is None:
            flags.append(f"{k}: on {'the estimate' if p is None else 'the proposed SOV'} only"); continue
        d = p - s
        print(f"{k:22} {p:10,.0f} {s:13,} {d:+9,.0f}")
        if k in CAPS and p / CONTRACT_SUM > CAPS[k]:
            flags.append(f"{k}: proposed ${p:,.0f} is {p / CONTRACT_SUM:.1%} of the contract, over the {CAPS[k]:.1%} cap")
        if d > FRONT_LOAD_TOL * s:
            flags.append(f"{k}: proposed ${p:,.0f} is {d / s:.0%} over its proportional ${s:,}; front-loaded unless the backup supports it")
    pt = sum(prop.values())
    print(f"{'Total':22} {pt:10,.0f} {sum(sov.values()):13,} {pt - CONTRACT_SUM:+9,.0f}")
    if round(pt) != CONTRACT_SUM:
        flags.append(f"Proposed SOV totals ${pt:,.0f}, not the ${CONTRACT_SUM:,} contract sum")

print("\nFlags (clear each before the SOV goes out with the first pay application):")
for f in flags:
    print(" - " + f)
print("Arithmetic only. Line breakdown, caps and what the contract allows come from your contract and the owner; the SOV is approved by the architect or owner, not by this check.")
```

## Check the result

- Every value, citation or quantity traces back to a source document.
- Missing information is marked as missing, not filled in.

## Limits and recovery

- The check is arithmetic on the rows and rules you type. It cannot tell whether your contract requires a different breakdown (by area, spec section or material versus labor), whether general conditions, bonds or mobilization must be their own lines or spread, whether stored materials need separate lines, or whether an owner will accept a line split; read the contract and Division 01 for those. Proportional spread is a common, even-handed default, not a rule; if you carry markup differently, type it that way. Caps and tolerances here are typed example values, not a standard.
- Check your organization’s data policy before sharing project files with third-party tools.

**Stop or switch when:** The source cannot be verified, permissions are missing, or the result contains unsupported facts.

## Frequently asked questions

How does AI help with this?

Claude or ChatGPT, then Copilot in Excel or Gemini in Google Sheets: Claude or ChatGPT reads the estimate summary into one Estimate tab with your SOV Line for each cost code; Copilot or Gemini (or a short script) totals cost by line, spreads the contract sum in proportion to cost, rounds to the dollar so the lines total the contract exactly, and flags unmapped or duplicated codes, lines over your contract's caps, lines too big to bill monthly and proposed lines well above their proportional value. A person still checks: The mapping of codes to lines, every flag, the line total against the contract sum and any caps against the contract before the schedule goes out; the line breakdown and caps come from the contract and Division 01, and the schedule is approved by the architect or owner, not by the check.

How do I how do I turn my estimate into a schedule of values with AI so it adds up to the contract and isn't front-loaded??

Start from the estimate, not from the billing form: export or copy the summary by cost code with the cost of each code (not quantities or hours), plus the executed contract sum before any change orders. Read the contract and Division 01 for any required breakdown, caps on mobilization, bonds or general conditions, and whether those must be their own lines. Have Claude or ChatGPT read the estimate summary (upload the PDF or paste the export) into one Estimate tab: Code, Description, Cost, SOV Line. You decide the SOV Line names; group codes the way the work is installed and inspected, usually 10 to 30 lines, and keep the same lines for the whole job. It copies costs exactly, writes UNMAPPED instead of guessing a line, and lists any code that appears twice. On a Rules tab, type the contract sum, any caps your contract or the owner set (as a share of the contract), the largest share you are willing to bill in one line, and how far over its proportional value a line may sit before you call it front-loaded. Have Copilot in Excel or Gemini in Google Sheets (or the script below) total cost by line, multiply each by contract sum divided by total cost, round down to the dollar and give the leftover dollars to the lines with the largest fractions. The full step list is above.

Does this use an AI agent or regular software?

It is labeled AI assists: AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

What tools do I need?

Claude, ChatGPT, Microsoft Excel, Microsoft Copilot, Google Sheets, Gemini. Confirm license, version and cost with the vendor, and try it on a small non-confidential sample first.

Has this workflow been tested?

Workflow guide · not independently tested. Written from practitioner use. Labels apply to the steps described here, not every feature of a product. Links were checked when the page was written. The sample script below was run on the example rows shown.

## Where to go next

- [How do I search project documents with AI to answer field questions, then confirm the source?](https://aecagents.si/use-cases/project-document-search)
- [How do I compare construction schedule scenarios with AI-assisted scheduling tools?](https://aecagents.si/use-cases/schedule-optimization)
- [How do I spot schedule delays and quality problems early with schedule analytics?](https://aecagents.si/use-cases/schedule-health)
- [All Project Manager workflows](https://aecagents.si/roles/project-manager)
- [All Estimating and takeoff workflows](https://aecagents.si/tasks/estimating-takeoff)

## Evidence and maintenance

Written from practitioner use. Labels apply to the steps described here, not every feature of a product. Links were checked when the page was written. The sample script below was run on the example rows shown.

- [Claude (Anthropic) (vendor site)](https://www.anthropic.com/claude)
- [ChatGPT (vendor site)](https://chatgpt.com/)
- [Microsoft Excel (vendor site)](https://www.microsoft.com/microsoft-365/excel)
- [Microsoft Copilot (vendor site)](https://www.microsoft.com/microsoft-365/copilot)
- [Google Sheets (vendor site)](https://workspace.google.com/products/sheets/)
- [Gemini (vendor site)](https://gemini.google.com/)

## On this page

Start with a small sample and keep the original record open while you verify the result.

## How each workflow is labeled

Agent executes
:   An AI agent calls connected tools to carry out bounded actions. You set permissions and review the result.

AI assists
:   AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

Conventional automation
:   Rules or specialist software perform the task. No AI agent is required.