title: How do I check a subcontractor change order's markups and labor rates against the contract with AI before I approve it? | AEC Agents
url: https://aecagents.si/use-cases/change-order-markup-vs-contract-limits
description: Most change order fights are not about the work; they are about the arithmetic. A sub prices labor at a foreman rate that is not on the agreed rate sheet, takes 15 percent on material when the contract allows 10, takes the full own-work markup on a lower-tier sub's quote, adds markup on the markup line, or carries a bond percentage higher than the contract allows, and a total that looks reasonable gets approved. Have ChatGPT or Claude read the change order request PDF into one table of cost and markup lines, then have Copilot in Excel, Gemini in Google Sheets or a short script check every line against the markup limits and rate sheet you type from your own contract: extensions, agreed rates, markup percentage and base by category, markup on markup, bond, and missing backup, with a billed vs expected total. Whether the work is a change at all, and the quantities, stay with you.
last_modified: 2026-11-27
source: AEC Agents (free, open workflows; not engineering advice)
---

[AI assists](https://aecagents.si/use-cases/change-order-markup-vs-contract-limits#honesty-labels)Workflow guide · not independently tested

# How do I check a subcontractor change order's markups and labor rates against the contract with AI before I approve it?

Most change order fights are not about the work; they are about the arithmetic. A sub prices labor at a foreman rate that is not on the agreed rate sheet, takes 15 percent on material when the contract allows 10, takes the full own-work markup on a lower-tier sub's quote, adds markup on the markup line, or carries a bond percentage higher than the contract allows, and a total that looks reasonable gets approved. Have ChatGPT or Claude read the change order request PDF into one table of cost and markup lines, then have Copilot in Excel, Gemini in Google Sheets or a short script check every line against the markup limits and rate sheet you type from your own contract: extensions, agreed rates, markup percentage and base by category, markup on markup, bond, and missing backup, with a billed vs expected total. Whether the work is a change at all, and the quantities, stay with you.

Role
:   [Project Manager](https://aecagents.si/roles/project-manager)

Discipline
:   Construction

Tools
:   ChatGPT, Claude, Microsoft Copilot, Microsoft Excel, Google Sheets, Gemini

Updated
:   27 November 2026

Tool links listed below; vendor features and pricing change, so confirm with the vendor.

## Short answer

Use ChatGPT or Claude, then Copilot in Excel or Gemini in Google Sheets: ChatGPT or Claude reads the change order request and its backup into one table of cost, markup and bond lines; Copilot or Gemini (or a short script) recomputes every line, prices labor and equipment at your agreed rates, and flags math errors, off-sheet rates, markup over your contract limit or on the wrong base, markup on markup, bond over the limit and missing backup, with billed vs expected totals. Most change order fights are not about the work; they are about the arithmetic. A sub prices labor at a foreman rate that is not on the agreed rate sheet, takes 15 percent on material when the contract allows 10, takes the full own-work markup on a lower-tier sub's quote, adds markup on the markup line, or carries a bond percentage higher than the contract allows, and a total that looks reasonable gets approved. Have ChatGPT or Claude read the change order request PDF into one table of cost and markup lines, then have Copilot in Excel, Gemini in Google Sheets or a short script check every line against the markup limits and rate sheet you type from your own contract: extensions, agreed rates, markup percentage and base by category, markup on markup, bond, and missing backup, with a billed vs expected total. Whether the work is a change at all, and the quantities, stay with you. A person still checks: every flagged line against your subcontract change clause, the rate sheet in force and the field record before you approve, return or negotiate; entitlement and quantities stay with you.

## AI tie-in

**Tool:** ChatGPT or Claude, then Copilot in Excel or Gemini in Google Sheets

ChatGPT or Claude reads the change order request and its backup into one table of cost, markup and bond lines; Copilot or Gemini (or a short script) recomputes every line, prices labor and equipment at your agreed rates, and flags math errors, off-sheet rates, markup over your contract limit or on the wrong base, markup on markup, bond over the limit and missing backup, with billed vs expected totals.

### Prompt 1

```
Read this change order request [upload the PDF and its backup] and build a Lines table with one row per line: COR, Line, Category (Labor, Material, Equipment, Sub, Markup, Bond), Description, Qty, Unit, Rate, Amount and Backup, copied exactly. On Markup and Bond lines put the base in Qty and the percent in Rate. Write NOT SHOWN instead of guessing. List every line with no backup attached.
```

### Prompt 2

```
EXAMPLE DATA ONLY (not from a real project). Lines tab: COR lines with COR, Line, Category, Description, Qty, Unit, Rate, Amount and Backup. Rates tab: agreed labor and equipment rates. Rules tab typed from my own subcontract: OH&P limit per category, bond percent and base, and no markup on markup. Write Excel formulas (or a step-by-step Copilot plan) that recompute each line, price labor and equipment at the agreed rate, flag math errors, off-sheet rates, markup over the limit or on the wrong base, markup on markup, bond over the limit and missing backup, and show billed vs expected total per COR. Use only my rows and rules; do not supply any markup percentage or rate from memory.
```

**Human check:** Every flagged line against your subcontract change clause, the rate sheet in force and the field record before you approve, return or negotiate; entitlement and quantities stay with you.

## The problem

Check a subcontractor change order's markups and rates against the contract limits with AI before you approve it. This is a common, time-consuming task for a project manager.

## What this workflow does

Most change order fights are not about the work; they are about the arithmetic. A sub prices labor at a foreman rate that is not on the agreed rate sheet, takes 15 percent on material when the contract allows 10, takes the full own-work markup on a lower-tier sub's quote, adds markup on the markup line, or carries a bond percentage higher than the contract allows, and a total that looks reasonable gets approved. Have ChatGPT or Claude read the change order request PDF into one table of cost and markup lines, then have Copilot in Excel, Gemini in Google Sheets or a short script check every line against the markup limits and rate sheet you type from your own contract: extensions, agreed rates, markup percentage and base by category, markup on markup, bond, and missing backup, with a billed vs expected total. Whether the work is a change at all, and the quantities, stay with you.

**How it works:** AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

**Your checkpoint:** The check only sees the lines, rate sheet and rules you give it. It cannot tell whether the work is extra to the contract, whether the hours and quantities are real, whether a rate sheet was superseded, or how your contract treats items like small tools, supervision or insurance, so you confirm the rules from your own subcontract and the field record before you approve, return or negotiate the COR. Markup limits come from your contract, never from the AI.

## Before you start

- Access to the named tool; confirm license, version and cost with the vendor.
- A small, non-confidential sample to try the workflow on first.
- A qualified person to review the output before it is used.

### Tools and access

- [ChatGPT](https://chatgpt.com/)
- [Claude (Anthropic)](https://www.anthropic.com/claude)
- [Microsoft Copilot](https://www.microsoft.com/microsoft-365/copilot)
- [Microsoft Excel](https://www.microsoft.com/microsoft-365/excel)
- [Google Sheets](https://workspace.google.com/products/sheets/)
- [Gemini](https://gemini.google.com/)

## Follow the steps

1. Type the change clause terms from your own subcontract into a Rules tab: the allowed overhead and profit percentage for each category (own labor, material, equipment, lower-tier sub), the bond or insurance percentage and what it applies to, and whether markup is allowed on markup. Put the agreed labor and equipment rate sheet on a Rates tab.
2. Have ChatGPT or Claude read the change order request and its backup into a Lines table: COR, line, category (Labor, Material, Equipment, Sub, Markup, Bond), description, quantity, unit, rate and amount copied exactly, the markup base and percentage on markup lines, and what backup is attached. It writes NOT SHOWN instead of guessing.
3. Have Copilot in Excel or Gemini in Google Sheets (or the script below) recompute each cost line (quantity times rate), price labor and equipment at the agreed rate, and flag every math error, off-sheet rate and line with no backup.
4. Check each markup line: the percentage against your limit for that category, the base against the corrected cost for that category, and any markup taken on a markup, bond or tax line that your contract does not allow.
5. Recompute the bond on the corrected subtotal, then show billed total, expected total and the difference for each COR, with every flag listed by line number.
6. Return the COR with the flagged lines, or approve the corrected amount. The flags are arithmetic; entitlement, the quantities and any negotiation stay with you.

## Try a small example

EXAMPLE DATA ONLY: fictional change order lines, rates and contract limits for practice, not from a real project or a published trial. Paste the Sample input into Copilot or Gemini with the Starter prompt, then compare your results to Expected output.

### Sample input

```
Lines tab (example, saved as cor.csv; on Markup and Bond lines Qty is the base and Rate is the percent)
COR,Line,Category,Description,Qty,Unit,Rate,Amount,Backup
COR-07,1,Labor,Journeyman electrician,24,hr,98.00,2352.00,Timesheets
COR-07,2,Labor,Foreman electrician,8,hr,112.00,896.00,Timesheets
COR-07,3,Material,Floor boxes and fittings,1,ls,1840.00,1840.00,Supplier quote
COR-07,4,Equipment,Scissor lift 19 ft,2,day,95.00,190.00,
COR-07,5,Sub,Core drilling sub,1,ls,1200.00,1200.00,Sub quote
COR-07,6,Markup,OH&P on Labor,3248.00,base,15,487.20,
COR-07,7,Markup,OH&P on Material,1840.00,base,15,276.00,
COR-07,8,Markup,OH&P on Equipment,190.00,base,10,19.00,
COR-07,9,Markup,OH&P on Sub,1200.00,base,10,120.00,
COR-07,10,Bond,Bond,6570.20,base,1.5,98.55,
COR-08,1,Labor,Journeyman carpenter,16,hr,86.00,1376.00,Timesheets
COR-08,2,Labor,Apprentice carpenter,16,hr,58.00,1028.00,Timesheets
COR-08,3,Material,Fire-rated blocking lumber,1,ls,410.00,410.00,
COR-08,4,Markup,OH&P on Labor,2404.00,base,15,360.60,
COR-08,5,Markup,OH&P on Material,410.00,base,10,41.00,
COR-08,6,Markup,OH&P on Markup,401.60,base,10,40.16,

Rates tab (example, saved as rates.csv; type yours from your own agreed rate sheet)
Item,Rate
Journeyman electrician,98.00
Foreman electrician,108.00
Scissor lift 19 ft,95.00
Journeyman carpenter,86.00
Apprentice carpenter,58.00

Rules typed by you from your own subcontract (example values): OH&P 15% on own labor, 10% on material, 10% on equipment, 5% on lower-tier sub work; bond 1% on cost plus allowed markup; no markup on markup; backup required for material, equipment and sub lines; amounts within $1 are rounding
```

### Starter prompt

```
EXAMPLE DATA ONLY (not from a real project). Lines tab: change order request lines with COR, Line, Category (Labor, Material, Equipment, Sub, Markup, Bond), Description, Qty, Unit, Rate, Amount and Backup; on Markup and Bond lines Qty is the base and Rate is the percent. Rates tab: agreed hourly and daily rates by item. Rules tab (typed from my own contract): OH&P limits of 15% on labor, 10% on material, 10% on equipment, 5% on lower-tier sub work; bond 1% on cost plus allowed markup; no markup on markup. Write Excel formulas (or a step-by-step Copilot plan) that recompute each line, price labor and equipment at the agreed rate, flag math errors, off-sheet rates, missing backup, markup over the limit, a markup base that does not match the corrected cost, markup on markup and bond over the limit, and show billed total, expected total and difference per COR. Use only my rows and my rules; do not supply any markup percentage or rate from memory.
```

### Expected output

```
Expected results on this example (output of the script below on these rows)
COR-07: billed $7,478.75  expected $7,263.31  difference $215.44  (6 flags)
   ! line 2 Foreman electrician: rate 112.00 vs agreed 108.00
   ! line 4 Scissor lift 19 ft: no backup attached
   ! line 6 OH&P on Labor: base $3,248.00 vs corrected Labor cost $3,216.00
   ! line 7 OH&P on Material: 15% vs 10% allowed
   ! line 9 OH&P on Sub: 10% vs 5% allowed
   ! line 10 Bond: 1.5% vs 1% allowed

COR-08: billed $3,255.76  expected $3,100.60  difference $155.16  (4 flags)
   ! line 2 Apprentice carpenter: 16 x 58.00 = $928.00, billed $1,028.00
   ! line 3 Fire-rated blocking lumber: no backup attached
   ! line 4 OH&P on Labor: base $2,404.00 vs corrected Labor cost $2,304.00
   ! line 6 OH&P on Markup: markup taken on 'Markup', which is not an allowed base

Flags only. Whether the work is a change, and the quantities, are checked against the contract and the field record before you approve or return the COR.

Read it this way: COR-07 is $215.44 high. The foreman rate is $4 over the rate sheet, which also inflates the labor markup base; material carries 15% where 10% is allowed; the core drilling sub got the 10% own-work markup instead of 5%; and the bond is 1.5% instead of 1%. The lift has no rental backup. COR-08 is $155.16 high: the apprentice line is extended at $1,028 when 16 x 58.00 is $928, the labor markup was then taken on the wrong base, and line 6 takes 10% on the markup lines themselves. None of this says whether the floor boxes or the blocking are a change; that is a separate review.

Suggested Excel logic (write against your own sheet layout)
- Extension: =IF(ABS(Qty*Rate-Amount)>1,"MATH","") on every cost line.
- Agreed rate: =XLOOKUP(Description,Rates[Item],Rates[Rate],"NOT ON SHEET") on Labor and Equipment lines, flag when it differs from Rate.
- Corrected cost by category: SUMIFS of Qty times agreed rate (or Amount when no rate applies) by COR and Category.
- Markup: XLOOKUP the limit for the category named after ' on '; flag when Rate is over it, when Qty differs from the corrected cost, or when the base is Markup, Bond or Tax.
- Bond: corrected cost plus allowed markup, times the allowed bond percent.
- Summary: billed total, expected total and difference per COR with COUNTIFS of flags.

Same check as a short Python script (our own code; reads the rows above saved as cor.csv and rates.csv)
import csv
from collections import defaultdict
# Rules typed by you from YOUR contract's change clause (example values, not advice)
MARKUP_LIMIT = {"Labor": 15.0, "Material": 10.0, "Equipment": 10.0, "Sub": 5.0}  # percent OH&P
BOND_LIMIT = 1.0                       # percent of cost plus allowed markup
RATED = {"Labor", "Equipment"}         # must match the agreed rate sheet
NEEDS_BACKUP = {"Material", "Equipment", "Sub"}
TOL = 1.00                             # dollars of rounding allowed

rates = {r["Item"].strip(): float(r["Rate"]) for r in csv.DictReader(open("rates.csv"))}
cors = defaultdict(list)
for r in csv.DictReader(open("cor.csv")):
    cors[r["COR"]].append({k: v.strip() for k, v in r.items()})
money = lambda x: f"${x:,.2f}"

for cor, lines in cors.items():
    flags, billed_cost, fair_cost = [], defaultdict(float), defaultdict(float)
    for r in lines:                    # cost lines
        cat, desc = r["Category"], r["Description"]
        if cat not in MARKUP_LIMIT: continue
        qty, rate, amt = float(r["Qty"]), float(r["Rate"]), float(r["Amount"])
        tag = f"line {r['Line']} {desc}"
        billed_cost[cat] += amt
        fair = qty * rate
        if abs(fair - amt) > TOL:
            flags.append(f"{tag}: {qty:g} x {rate:.2f} = {money(fair)}, billed {money(amt)}")
        if cat in RATED:
            if desc in rates:
                if abs(rates[desc] - rate) > 0.005:
                    flags.append(f"{tag}: rate {rate:.2f} vs agreed {rates[desc]:.2f}")
                fair = qty * rates[desc]
            else:
                flags.append(f"{tag}: not on the agreed rate sheet")
        if cat in NEEDS_BACKUP and not r["Backup"]:
            flags.append(f"{tag}: no backup attached")
        fair_cost[cat] += fair
    allowed_markup = sum(round(fair_cost[c] * MARKUP_LIMIT[c] / 100, 2) for c in fair_cost)
    for r in lines:                    # markup lines
        if r["Category"] != "Markup": continue
        on, base, pct = r["Description"].split(" on ")[-1], float(r["Qty"]), float(r["Rate"])
        tag = f"line {r['Line']} {r['Description']}"
        if on not in MARKUP_LIMIT:
            flags.append(f"{tag}: markup taken on '{on}', which is not an allowed base")
            continue
        if pct > MARKUP_LIMIT[on] + 1e-9:
            flags.append(f"{tag}: {pct:g}% vs {MARKUP_LIMIT[on]:g}% allowed")
        if abs(base - fair_cost[on]) > TOL:
            flags.append(f"{tag}: base {money(base)} vs corrected {on} cost {money(fair_cost[on])}")
    subtotal = sum(fair_cost.values()) + allowed_markup
    bond = 0.0
    for r in lines:
        if r["Category"] != "Bond": continue
        pct = float(r["Rate"])
        if pct > BOND_LIMIT: flags.append(f"line {r['Line']} Bond: {pct:g}% vs {BOND_LIMIT:g}% allowed")
        bond = round(subtotal * min(pct, BOND_LIMIT) / 100, 2)
    billed = sum(float(r["Amount"]) for r in lines)
    expected = subtotal + bond
    print(f"{cor}: billed {money(billed)}  expected {money(expected)}  difference {money(billed - expected)}  ({len(flags)} flags)")
    for f in flags: print(f"   ! {f}")
    print()
print("Flags only. Whether the work is a change, and the quantities, are checked against the contract and the field record before you approve or return the COR.")
```

## Check the result

- Every value, citation or quantity traces back to a source document.
- Missing information is marked as missing, not filled in.

## Limits and recovery

- The check only sees the lines, rate sheet and rules you give it. It cannot tell whether the work is extra to the contract, whether the hours and quantities are real, whether a rate sheet was superseded, or how your contract treats items like small tools, supervision or insurance, so you confirm the rules from your own subcontract and the field record before you approve, return or negotiate the COR. Markup limits come from your contract, never from the AI.
- Check your organization’s data policy before sharing project files with third-party tools.

**Stop or switch when:** The source cannot be verified, permissions are missing, or the result contains unsupported facts.

## Frequently asked questions

How does AI help with this?

ChatGPT or Claude, then Copilot in Excel or Gemini in Google Sheets: ChatGPT or Claude reads the change order request and its backup into one table of cost, markup and bond lines; Copilot or Gemini (or a short script) recomputes every line, prices labor and equipment at your agreed rates, and flags math errors, off-sheet rates, markup over your contract limit or on the wrong base, markup on markup, bond over the limit and missing backup, with billed vs expected totals. A person still checks: Every flagged line against your subcontract change clause, the rate sheet in force and the field record before you approve, return or negotiate; entitlement and quantities stay with you.

How do I how do I check a subcontractor change order's markups and labor rates against the contract with AI before I approve it??

Type the change clause terms from your own subcontract into a Rules tab: the allowed overhead and profit percentage for each category (own labor, material, equipment, lower-tier sub), the bond or insurance percentage and what it applies to, and whether markup is allowed on markup. Put the agreed labor and equipment rate sheet on a Rates tab. Have ChatGPT or Claude read the change order request and its backup into a Lines table: COR, line, category (Labor, Material, Equipment, Sub, Markup, Bond), description, quantity, unit, rate and amount copied exactly, the markup base and percentage on markup lines, and what backup is attached. It writes NOT SHOWN instead of guessing. Have Copilot in Excel or Gemini in Google Sheets (or the script below) recompute each cost line (quantity times rate), price labor and equipment at the agreed rate, and flag every math error, off-sheet rate and line with no backup. The full step list is above.

Does this use an AI agent or regular software?

It is labeled AI assists: AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

What tools do I need?

ChatGPT, Claude, Microsoft Copilot, Microsoft Excel, Google Sheets, Gemini. Confirm license, version and cost with the vendor, and try it on a small non-confidential sample first.

Has this workflow been tested?

Workflow guide · not independently tested. Written from practitioner use. Labels apply to the steps described here, not every feature of a product. Links were checked when the page was written. The sample script below was run on the example rows shown.

## Where to go next

- [How do I search project documents with AI to answer field questions, then confirm the source?](https://aecagents.si/use-cases/project-document-search)
- [How do I compare construction schedule scenarios with AI-assisted scheduling tools?](https://aecagents.si/use-cases/schedule-optimization)
- [How do I spot schedule delays and quality problems early with schedule analytics?](https://aecagents.si/use-cases/schedule-health)
- [All Project Manager workflows](https://aecagents.si/roles/project-manager)
- [All Schedules, submittals and project controls workflows](https://aecagents.si/tasks/project-controls)

## Evidence and maintenance

Written from practitioner use. Labels apply to the steps described here, not every feature of a product. Links were checked when the page was written. The sample script below was run on the example rows shown.

- [ChatGPT (vendor site)](https://chatgpt.com/)
- [Claude (Anthropic) (vendor site)](https://www.anthropic.com/claude)
- [Microsoft Copilot (vendor site)](https://www.microsoft.com/microsoft-365/copilot)
- [Microsoft Excel (vendor site)](https://www.microsoft.com/microsoft-365/excel)
- [Google Sheets (vendor site)](https://workspace.google.com/products/sheets/)
- [Gemini (vendor site)](https://gemini.google.com/)

## On this page

Start with a small sample and keep the original record open while you verify the result.

## How each workflow is labeled

Agent executes
:   An AI agent calls connected tools to carry out bounded actions. You set permissions and review the result.

AI assists
:   AI drafts or analyzes. A person operates the tools, checks the work, and takes action.

Conventional automation
:   Rules or specialist software perform the task. No AI agent is required.